Location: Hopewell, NJ

The Problems:

  • Insufficient Storage and Living Space

The Goal:

The primary goal of this project is to expand the home to better accommodate a growing family.

[Proposed Plans]

The Dream:

Create an all-day, every-day living space that every member of the family is able to enjoy.

The Timeline:

March 11, 2019 – June 3, 2019

Week 1: Demo Phase 1, Excavation, Concrete/Masonry, Building Inspection

Week 2: Demo Phase 2, Framing Phase 1

Week 3: Roofing, Siding, Exterior Window & Door Installation, Rough Trades, Framing Phase 2

Week 4: Rough Trades, Rough Inspections

Week 5: Insulation

Week 6: Drywall

Week 7: Drywall, Interior Door Installation,

Week 8: Exterior Stairs and Deck Installation

Week 9: Tile, Cabinetry

Week 10: Cabinetry, Interior Trim

Week 11: Interior Trim, Paint, Appliance Installation

Week 12: Finish Trades, Carpet Installation

Week 13: Final Inspections

The Progress (updated weekly)

Week 1:

All pre-construction site checks and inspections have been completed.

Week 2:

Week 2 started very strong, with little to no issue. Unfortunately, the weather was not kind. The project was halted due to 2 full days of rain.

Week 3:

The project is moving smoothly with framing wrapping up. The project is behind schedule due to two days of rain in the previous week.

Week 4:

Week 4 had a very rough start. We had multiple days of bad weather that caused additional project delays. This put us exactly on week behind schedule.

Week 5:

During Week 5 our team was able to complete all rough trades and install Siding.

Week 6:

Week 6 was an extremely successful week. Insulation, Gutter and Fascia installations were completed along with Rough Trade inspections. Allowing us to Prep Drywall.

Progress Photos

Week 7:

Drywall installation is underway and is scheduled to be completed during week 8.

Week 8:

Drywall and Interior door installations were completed. Exterior stair and Deck Installations has begun. Tile is prepped for next week’s installation.

Week 9:

The deck installations was completed. Interior Trim & Millwork have begun and is scheduled to be completed on Tuesday Morning. Tile work had multiple delays and is now behind schedule. As a result, Cabinetry Install is also behind schedule.

Week 10:

Tile and Cabinetry installations have been completed. Interior Trim is now underway.

Week 11:

Appliance and Interior Trim installations have been completed. The walls have been prepped and primed (homeowners decided to paint the home themselves.)

Week 12:

All final trades installations are underway.

Week 13:

All Final trade installations are now complete.

Week 14:

The wrong carpet was shipped to job site. We are currently waiting for the correct carpet to be delivered.

Week 15:

Carpet was installed with no issue. All final inspections were passed.

Click Here To See The Completed Project

Leave a Reply

*

Planning a renovation?

Get a free no-obligation quote for your renovation in seconds

  • This field is for validation purposes and should be left unchanged.
  • You’ll receive a response from a specialist within 24 hours

  • Expert face-to-face advice for your renovation project

  • There’s absolutely no pressure or commitment to buy.

  • No surprises, no hidden fees, and no extras.

Call Now Button